Malooga Investor & Community Update – September 2025
September was an exciting and productive month for Malooga as we continued building momentum toward the opening of our Main Line location. Alongside significant construction progress, we had the pleasure of connecting with our future neighbors and guests through local community events.
Sharing Malooga with the Community
We were delighted to take part in the Narberth Farmer’s Market and Narberth Music Festival, where we shared complimentary samples and introduced guests to Malooga’s signature flavors. These events gave us a wonderful opportunity to engage directly with the community, build excitement for our upcoming opening, and showcase the hospitality that defines who we are.
Construction Progress
Our build-out is moving forward on schedule, with several key milestones reached this month:
- ✅ Framing has been completed
- ✅ Plumbing through framing
- ✅ Millwork team completed on-site measurements
- ✅ High-voltage electrical wiring
- ✅ Permit for hood installation has been officially granted
What’s Next
Looking ahead to October, our team is focused on the next phase of work, including:
- HVAC unit installation
- Hood installation
- Health Department application submission
- Wall roughing and preparation
- Hiring key leadership positions
We’re grateful for the steady progress and the dedication of everyone involved. Thank you to our investors, community, and supporters for your continued trust and enthusiasm. Each step brings us closer to opening our doors and sharing the warmth of Malooga.
Follow our journey at www.maloogacatering.com and on Instagram @maloogacatering and @maloogamainline.